VILNYI construction progress and completion dates

Planned completion: building 2 — Q4 2026, buildings 1 and 3 — Q3 2027, building 4 — Q4 2027. The dates are planned, per lun.ua (as of September 15, 2026), and may change.

39 monthly photo reports, 252 photos from July 2023 to September 2026.

BuildingFloorsStatusCompletion (planned)
116under construction (as of September 15, 2026)Q3 2027
26under construction (as of September 15, 2026)Q4 2026
317under construction (as of September 15, 2026)Q3 2027
410preparatory works (as of September 15, 2026)Q4 2027

September 2026

September 15, 2026 · 10 photos

August 2026

August 27, 2026 · 10 photos

July 2026

July 13, 2026 · 10 photos

June 2026

June 22, 2026 · 10 photos

Earlier months

Photo: LUN (lun.ua) / VILNYI Group